Temporary chilled-water piping installed to maintain cooling during scheduled equipment upgrades at the VA Hospital.
How the project came together.
URE installed the temporary piping system needed to keep cooling service available while permanent equipment was being upgraded.
The temporary system had to support uninterrupted operation for critical hospital functions throughout the scheduled work.
Piping installation and tie-in sequencing were coordinated around hospital operations and the equipment-upgrade schedule.